Water Raw Main - Huntington Wellfield

This project is to design, permit and construct a new raw water main from the Huntington Wellfield to the West Water Treatment Facility and install the required equipment to activate the existing well (new pump, piping, controls, etc.). Project includes approx. 7,500 LF of 16"raw water main and will offer the City a new raw water supply to provide redundancies in the water supply system and ultimately serve as additional capacity within the water supply system.  

April 2019 - Agenda item has been rescheduled. Commission date TBD. Staff has scheduled a meeting with CPH to discuss the BODR.

March 2019 - Agenda item prepared for Phases 2 to 5 to go to commission 4/3/2019.Task 1 amendment is being routed for signatures.  

February 2019 - Well redevelopment was advertised and the requisition is in progress. Met with consultant about scope of work Phases 2 & 3. Preparing agenda item for either 3/20/19 or 4/3/19. 

January 2019 - Consultant completing surveying for existing conditions and ecological impact study. Between 30 and 60% complete. 

December 2018 - 30% design documents submitted and reviewed. Updated schedule provided. 

November 2018 - Well redevelopment task removed from the Engineer's scope and will be completed independently. Staff requested an updated schedule. 

October 2018 - Data has been provided to consultant. Staff requested an updated schedule.