HMII3 Planning/PDR/Design/Construction

Phase III Project consists of construction of a gravity sewer collection system, pumping station, a force main and storm water drainage improvements in the area generally bounded by Pembroke Road to the north of SW 64 Avenue and to the east of SW 25 Street to the south, and the Turnpike to the west, within the public right-of-way. The Preliminary Design (PDR) effort will evaluate and identify system requirements required to efficiently design the wastewater collection/stormwater management system within the Phase III area. Project offers the means to eliminate out dated and non functioning septic tanks through a central wastewater collection system. 


  1. January 2019 
  2. February 2019
  3. March 2019
  4. April2019

January 2019 - HMII3 Project Update                                                                                                                                                                          

Wastewater –Reynolds Construction utilizing two sanitary sewer installation crews. One crew is installing gravity sewer mains along SW 20th Court, east of SW 67th Avenue toward SW 66th Avenue and the second crew is installing gravity sewer mains along SW 19th Street between SW 68th Avenue and SW 66th Avenue.                                                                                                                                                                                                                           NOTE – First lift of asphalt has been installed at the following locations: SW 68th Avenue from SW 25th Street to Pembroke Rd


  1. October 2018
  2. November 2018
  3. December 2018

October 2018 - HMII3 Project Update                                                                                                                                                                                    

Sewer Installation - Reynolds Construction continued working with two sewer crews. One of the crews continued installing sewer along SW 67th Terrace. The second crew continued working on adjusting sewer laterals to grade on location where the sewer main has already been installed. Sewer installation is completed on all the side streets west of SW 68th Avenue, including SW 68th Avenue from SW 25th Street to Pembroke Road. Sewer installation is also completed along SW 25th Street from SW 64th Avenue to SW 68th Avenue.