West Water Treatment Lab and Office Space

Expansion of laboratory, office space, and general building at the West Water Treatment Plant.  

December 2018 - Project advertised for bids and bids were opened the week of 11/19/18 with results that doubled the estimate. Project under review.  

November 2018 - The bids were extended from October 31, 2018 to November 7, 2018. Staff will work with Procurement to review and process the bids. Staff will schedule the item for award at one of the January 2019 Commission meetings.   

October 2018 - Advertisement for bid is scheduled for September 30, 2018. The Architect proposal to cover the lab equipment in the mechanical yard layout was reviewed and was not accepted.